C0988 - We are requesting confirmation of the date of payment of contact progress billing periods below, by METRO to Walsh/Shea-CC for the Crenshaw-LAX Corridor Transit Project for which we are the Masonry Subcontractor: October 2018


Received

February 4, 2019 via web


Departments

Public Records Requests

Documents

Public

(loading...)

Staff

Point of Contact

Williams

Request Closed   Hide Public

Metro paid WSCC for the October 2018 progress payments on December 11, 2018. 